A typical 4 kW solar panel system, about 9 panels, costs roughly £5,500 to £8,000 fitted in 2026, with no VAT to pay until 31 March 2027. Adding a 5 kWh battery at the same time adds roughly £3,000 to £4,500.
Government data on more than 250,000 home installations in 2025/26 backs this up. The median price was about £1,550 to £1,600 per kW, and bigger systems cost less per kW than small ones. Below we show prices by system size, what a quote should and should not include, why prices in our area sit a little above the national average, and a checklist for comparing two quotes fairly.
Solar panel costs by system size
These are typical fitted prices from 2026 UK cost guides, at 0% VAT. Panel counts assume modern panels of around 440 watts.
| System size | Panels (about) | Solar panels only | With a 5 kWh battery |
|---|---|---|---|
| 3 kW | 7 | £4,500 to £6,500 | £7,500 to £11,000 |
| 4 kW | 9 | £5,500 to £8,000 | £8,500 to £12,500 |
| 5 kW | 11 to 12 | £7,000 to £9,500 | £10,000 to £14,000 |
| 6 kW | 14 | £8,000 to £11,500 | £11,000 to £16,000 |
The battery column adds a 5 kWh battery at £3,000 to £4,500 to the solar price. A larger battery of around 10 kWh adds about £4,500 to £6,500 instead. Fitting a solar and battery system together usually means one visit, one set of electrical work and one inverter that handles both, so it tends to cost less than adding one later.
The government benchmark. The Department for Energy Security and Net Zero (DESNZ) publishes the cost of every certified home solar installation each year. For 2025/26 (April 2025 to March 2026, published May 2026):
- systems up to 4 kW had a median price of £1,595 per kW (average £1,808);
- systems of 4 to 10 kW had a median of £1,546 per kW (average £1,622).
So a 4 kW system at the national median works out at about £6,200 to £6,400. The fixed costs of a job, such as scaffolding, the inverter, the paperwork and the visit, are spread over more panels on a bigger system, which is why the price per kW falls as size goes up.
Not sure what size you need? Our guide to how many solar panels you need works it out from your electricity use and roof space.
Our prices. As a budgeting guide, we work on roughly £1,500 to £1,800 per kW installed for a straightforward home system. Your fixed price comes after the free survey, and it does not change.
What a solar quote should include
Two quotes for the “same” system can be £2,000 apart simply because one includes things the other leaves out. These are the items to look for.
| Item | Usually in the quote? | Typical cost if it is extra |
|---|---|---|
| Panels, inverter, mounting kit, cabling and fitting | Yes | Part of the main price |
| Scaffolding | Usually, but check | About £600 to £2,000, more for tall or awkward roofs |
| Bird-proofing mesh around the panels | Often extra | About £300 to £1,000 |
| New consumer unit (fuse board) if yours is old or full | Usually extra, found at survey | About £300 to £1,200, at the top end in the South East |
| Roof repairs found at survey | Extra | Depends on the roof |
| Network operator paperwork (G98 or G99) | Should be | The network operator does not normally charge a home for this |
| Electrical certificate and Building Regulations notification | Should be | Part of the job |
| Battery | Only if you ask | See the table above |
What our quotes include. Our quotes list the panels, inverter, mounting kit, wiring, labour, testing, commissioning and certification, and say clearly whether scaffolding, bird-proofing and the network operator paperwork are included. A new consumer unit is not automatically included, because it is not always needed. If your home needs any electrical upgrades, we identify and price them at the survey, so there are no surprises later.
How long the work takes. For a straightforward installation, allow several days, often around a working week. The scaffolding usually goes up a few days beforehand, and the installation itself commonly takes one or two days.
What makes solar panels cost more
The national averages above hide a wide spread. These are the things that move a price up or down.
- System size. More panels cost more in total but less per kW, because scaffolding, labour and paperwork are largely fixed.
- Your roof. Slate is fragile and each slate is nailed in place, so fitting brackets takes more care and replacement slates. Solar guides put a slate install at one or two days longer than average. Very steep, tall or complicated roofs need more scaffolding.
- Access. If scaffolding has to stand on the pavement, the council has to license it. Wandsworth, for example, asks for applications at least five working days before the scaffold goes up.
- Your electrics. An old or full consumer unit, or a long cable run from the roof to the fuse board, adds work.
- Shading. Panels on a partly shaded roof may need optimisers or microinverters to protect output, which adds to the kit cost.
- A battery. It is the biggest single addition, and it needs a hybrid inverter or its own battery inverter.
The things that usually push a job above the typical price are difficult access or complex scaffolding, panels spread across several roof slopes, roof repairs, premium equipment, batteries, long cable routes, or electrical or network upgrades. Roof-integrated panels, which sit in the roof in place of tiles, can also cost more than panels mounted above the existing roof.
A typical semi round here. For a 3-bed semi in our area, a sensible starting estimate is around 3.5 to 4.5 kW, roughly 8 to 10 modern panels, with a budget of about £5,500 to £8,000 installed.
Solar panel costs in Surrey, Sussex, Hampshire and south west London
Prices here run a little above the national average. In the DESNZ figures for 2025/26, average prices per kW in the South East were a little higher than the Great Britain average. Higher labour and scaffolding costs are the likely reasons.
Which network operator you are on. Every solar system has to be registered with the local electricity network operator (DNO). South west London, most of Surrey and most of Sussex are on UK Power Networks. Hampshire, the far west of Surrey around Farnham, Camberley and Haslemere, and the Chichester end of West Sussex are on SSEN. We check which operator covers your postcode at the survey. The rules are the same for both:
- G98: an inverter of up to 3.68 kW on a normal single-phase supply. The installer fits the system and notifies the network operator within 28 days.
- G99: anything bigger, which can include a larger battery. The installer must get approval before the system is switched on, which can take several weeks, often 4 to 8. There is normally no fee for a home, but it adds time, and occasionally the network operator limits how much you can export.
Planning in conservation areas, national parks and listed buildings. Panels on a house roof are usually permitted development, so no planning application is needed. That still applies in most conservation areas, though wall-mounted panels on a wall facing a road are not allowed there. Listed buildings need consent, and some homes have an Article 4 direction that removes permitted development rights. The same rule applies in the Surrey Hills National Landscape, the South Downs National Park and the New Forest National Park, all of which are in our area, so it is worth checking with your council first. If you do need to apply, a householder planning application in England costs £548.
How the price changes when 0% VAT ends
Home solar panels and batteries in Great Britain are zero-rated for VAT until 31 March 2027. From 1 April 2027 they are due to go back to the reduced rate of 5%. That applies to batteries fitted with new panels, added to existing panels or installed on their own.
5% adds £50 for every £1,000 of the price:
| System | Price at 0% VAT | Extra at 5% VAT |
|---|---|---|
| 4 kW solar | £5,500 to £8,000 | £275 to £400 |
| 4 kW solar with a 5 kWh battery | £8,500 to £12,500 | £425 to £625 |
| 6 kW solar with a 5 kWh battery | £11,000 to £16,000 | £550 to £800 |
It is a real saving, but not one worth rushing a decision for. If your install is booked close to the end of March 2027, ask your installer how the change would apply to your invoice. HMRC’s VAT notice on energy-saving materials has the detail.
How to compare two solar quotes fairly
Put your quotes side by side and check each of these. If a quote does not answer one, ask.
- The same system size, in kW, with the panel make, model and wattage named. “10 panels” means little without the wattage.
- The inverter: make, size and warranty. If you might add a battery later, ask whether it is battery-ready.
- The battery’s usable capacity, not just the headline kWh. A “10 kWh” battery may give you 8 to 9 kWh of real use.
- Scaffolding, bird-proofing, consumer unit and roof repairs: included, excluded, or “to be confirmed”?
- Who handles the G98 or G99 paperwork, the electrical certificate and the Building Regulations notification.
- A fixed price or an estimate. Was the price set after someone looked at your roof, or from a satellite image?
- Who does the work. The company’s own engineers, or subcontractors?
- What the savings figures assume. Some quotes include payments for the electricity you export. Most suppliers require an MCS-certified installation before they pay for exports, so check what a quote’s savings are based on.
- The warranties: product and performance warranties on the panels, the inverter warranty, and the installer’s own workmanship guarantee.
How we quote. Our survey is always free. We check the condition of your roof and whether the rafters and trusses can take the extra weight, something an online quote cannot see. See our solar panels page for how we design and fit a system. We choose the panel brand at the survey to suit the job rather than pushing a default; the panels we fit are Aiko and DAS Solar. The work is done by our own employed engineers, never subcontractors, and our price is fixed and genuinely stays fixed. If solar does not make sense for your home, we will tell you, even if that means talking you out of it.
Is the cost worth it?
That depends on how much of the electricity you use yourself. Each unit your panels supply directly is one you do not buy, worth about 26p at the October to December 2026 price cap of 26.32p per kWh. Our guide to whether solar panels are worth it works through savings and payback, and our guide to what size battery you need covers when a battery adds value.
Frequently asked questions
How much does a 4 kW solar panel system cost?
A 4 kW system, about 9 panels, typically costs £5,500 to £8,000 fitted in 2026, with no VAT until 31 March 2027. Government data for 2025/26 puts the national median at about £6,200 to £6,400 for this size, and South East prices run a little higher. Scaffolding, your roof type and your electrics move the final figure, so a survey gives the real price.
How much do solar panels with a battery cost?
A 4 kW solar system with a 5 kWh battery typically costs £8,500 to £12,500 fitted in 2026. A 5 kWh battery on its own adds roughly £3,000 to £4,500, and a 10 kWh battery about £4,500 to £6,500. Fitting the battery at the same time as the panels usually costs less than adding it later, because the visit and electrical work are shared.
Is scaffolding included in the price of solar panels?
It usually is, but not always, so check the quote. Scaffolding typically costs about £600 to £2,000 depending on the height and shape of the roof and access to it. If the scaffold has to stand on the pavement, the council must license it, which adds cost and a few days’ notice. Ask for scaffolding to be listed as a line on the quote.
Will solar panels cost more after March 2027?
Probably a little. Solar panels and batteries are zero-rated for VAT in Great Britain until 31 March 2027, and the rate is due to return to 5% from 1 April 2027. That adds £50 for every £1,000, so about £275 to £400 on a typical 4 kW system. Panel prices themselves have been falling slowly, which may offset some of it.
Why do solar panel quotes vary so much?
Quotes differ in system size, panel and inverter brands, and what is included. One may include scaffolding, bird-proofing and a new consumer unit while another leaves them out or marks them “to be confirmed”. Some are fixed prices after a roof survey and others are estimates from a satellite image. Compare the same system size and the same inclusions before comparing the totals.
Do I have to pay to connect solar panels to the grid?
Normally not. Your installer registers the system with the local network operator: UK Power Networks or SSEN in our area. Systems with an inverter up to 3.68 kW are notified after installation. Larger systems need approval first, which can take several weeks. The network operator does not usually charge a home for either, although upgrades to the local network occasionally can be needed.
Get a price for your home
Every roof is different, so the figures above are a starting point. Try our instant solar estimate for a ballpark figure, or book a free survey for a fixed, written price. We cover Surrey, Sussex, Hampshire and south west London.